Fortec Case Study Smith U-Wraps

Fortec Case Study Smith U-Wraps

Date April 2013

Location: Clare Michigan

Contractor: Smiths Waterproofing

Engineer: M-DOT

Material Used: 600 gsm unidirectional carbon fiber #4550 Epoxy Resin

Project Scope: Strengthen Concrete Beams for shear reinforcement

Conclusion: U-Wraps were installed in 2 days to restore shear capacity without shutting down traffic flow.Fortec Case Study Smith U-Wraps Fortec Case Study Smith U-Wraps