Fortec Case Study Surmac

Fortec Case Study Surmac

Date: May 2015

Location: Broadway Loft Parking Garage San Antonio TX

Contractor: Surmac

Engineer: Bill Ciggelakis

Materials Used: 2 ft counter sunk carbon fiber staples, 4 inch carbon carbon grid and #4020 LPL epoxy

Project Scope: Metal pan concrete deck did not bond to Nelson Studs. We needed to develop a solution to deal with vertical deflection deck movement due to vehicle load traveling in aisles.

Conclusion: The large countersunk staples were used at 4 ft intervals to tie together concrete slabs. Carbon carbon grid was used for random cracking. Firefox cementitious overlay finished the restoration.